Function To Find Business Days Between Two Dates - Query Tuning

Mar 17, 2011

I have a query that uses a function to find the business days between two dates.It sums the total number of days between two dates per employee to find the total days for the past 30, 90, or 365 days.

The problem is that the query takes 21 second to return the last 30 days.Over 70 second to return the last 90 days and over 140 second to return the last 365 days.Do you know how I could tune the query to return faster? Below is the query for the last 30 days:

select dwt_emp_id, SUM((SELECT GET_BDAYS(DWT_DATE,DWT_CREATE_DATE) FROM DUAL))
from dwt_dvt_work_time where dwt_create_date > sysdate - 30
and dwt_hours > 4 and dwt_usr_uid_created_by <> -1 group by dwt_emp_id order by dwt_emp_id

Here's the function:
CREATE FUNCTION get_bdays (d1 IN DATE, d2 IN DATE)
RETURN NUMBER
IS total_days NUMBER(11,2);
holiday_days NUMBER(11,2);
[code]....

View 1 Replies


ADVERTISEMENT

PL/SQL :: Query To Calculate Business Days

May 20, 2013

i have table name order table . in that i have column name install date,order date.

the difference bet ween order date and install date should be greate than or equal to 3 working days.

fri and sat are holidays.

i need one query to find the difference betwwen orderdate and install date is greate than 3 working days

View 3 Replies View Related

SQL & PL/SQL :: Oracle Stored Function / Procedure To Calculate Number Of Working Days Between Two Dates

Feb 17, 2010

I want Oracle stored function/procedure to calculate number of working days between two dates. We need to exclude Firdays and Saturdays as there are weekend holidays and also exclude official holidasy that lie between two dates.

View 7 Replies View Related

SQL & PL/SQL :: Difference Between Business Days And Hours?

Sep 19, 2010

format of dtActivityStartDate/dtActivityFinishDate: 2010-09-17 14:50:51.150 Note: Both dtActivityStartDate/dtActivityFinishDate
vcActivityName = Process Request
usdFuncTimeCalc (vcActivityName,dtActivityStartDate, dtActivityFinishDate)

i need to calculate time elasped for that type of activity following are the rules:

(If Process Request is the activity)
Working Days: Monday through Saturday
Hours of Operation: 9AM 5PM

only working hours of day need to the counted like for example if it is sep 15 11 Am is dtActivityStartDate & Sep 17 is dtActivityFinishDate is 10 Am. then time elapsed is 11am to 5pm on sep 15 , 9 to 5 on sep 16 & 9 to 10 on sep 17 so total should be

6+ 8 + 1 = 15 hours + minutes.
format of date time: 2010-09-17 14:50:51.150
vcActivityName = Process Request
Don't worry about process request..

View 4 Replies View Related

PL/SQL :: Calculate Business Hours Between Two Dates Within A Cursor

Jul 24, 2013

I need a similar function to determinate difference between two dates, but i need other business hours; Monday - Friday: 9:00 - 21:00 (this is OK)Saturday: 09:00 - 14:00  (and this is my problem, how to add this condition in this function) 

View 4 Replies View Related

PL/SQL :: Query To Find Number Of Days Across Each Month

Oct 1, 2012

We have a requirement where we need to pay allowance for the employees based on their number of working days. Say for example if an employee worked from 03/Mar/2012 to 05/Apr/2012.

We have a fixed value for per month 300 Dirhams. But the Number of Days on March s 31 and Number of days in April is 30. So per day allowance for March day would be 300/31 and April would be 300/30.

We are looking for logic opr query which calculates first eh number of days in each month ( across months) and then calculate as below

Number of Working days in March is 31 - 3 + 1 = 29

Allowance A1 = (300 * 29 )/31

Number of Working days in April is 5 ( this also needs to find logical I am guess )
Allowance A2 = (300 * 5 )/30

Then A1 + A2.

The A(n) would be the total allowance where provided the number of month across.

View 10 Replies View Related

Finding Individual Dates Having Dates Plus 2 Days

Jan 26, 2011

I want to find the dates which have a date plus with in 2 days after this date. I mean group by 3 days each even the date i missing between two days. Actualy I want to find the start date where the employ was missing on job.

Basic concept is employes have allowed to use 10 personal leaves of a year. Each leave can be use for maximum 3 days.

If employ did not come on the job for one day or two days or three days, it shoul be count as ONE personal leave. And If employ is missing at job for four or five days, it should be count as 2 personal leaves.

seq date
------------------------------
101.01.10

205.01.10
306.01.10

410.01.10
512.01.10

613.01.10
714.01.10
815.01.10

916.01.10
1018.01.10

1119.01.10
1220.01.10
1321.01.10

1423.01.10

1526.01.10
1627.01.10

1729.01.10
1831.01.10

The result should be (Don't use Pl/Sql)

seq date
------------------------------
101.01.10
205.01.10
310.01.10
413.01.10
516.01.10
619.01.10
723.01.10
826.01.10
929.01.10

After finding these days I want to select the starting date of 5th personal leave. (which is 16.01.10).

I am not a expert of using SQL, but I think it could be possible with using partitioning a table on the givin reslult and further partition the reslut on rownum() as rn and the using case statement where rn = 5.

View 2 Replies View Related

SQL & PL/SQL :: Query To Find Missing Dates Between Two Columns In Given Month?

Sep 26, 2012

I need query to find the missing dates between two columns in given month.

CREATE TABLE emp_shift (
empno NUMBER(4),
fr_date DATE,
TO_DATE DATE,
shift VARCHAR2(1));
CREATE TABLE emp (
empno NUMBER(4)
);

[code].....

Required output is

MISSING_DATES EMPNO
---------------------- ----------
09-SEP-12 TO 11-SEP-12 7499
23-SEP-12 TO 26-SEP-12 7499
01-sep-12 TO 30-SEP-12 7521
01-sep-12 TO 30-SEP-12 7788

View 8 Replies View Related

PL/SQL :: Tuning Greater Than Predicate Query On Dates

Aug 2, 2012

I have the below query which is doing FTS and is very expensive causing load to timeout.

I did my analysis and found that table is having large number of records and hence FTS is taking long time causing timeout from app side.

I proposed to have this table partitioned but this is still pending with business and they in meantime want some solution other solution to fix this issue.

below is the query and plan

SELECT TRANSACTION_LOG.ID, TRANSACTION_LOG.USER_IDENTIFIER, TRANSACTION_LOG.START_TIME, TRANSACTION_LOG.END_TIME, TRANSACTION_LOG.REQUEST, TRANSACTION_LOG.RESPONSE ....

View 5 Replies View Related

SQL & PL/SQL :: Days Between Dates

Mar 14, 2012

I have not defined the table ( I only have privileges to query data).

I am unable to copy and paste my real code here, and the actual results from the run, as my company will fire me if I do so... so here is how things approximately look like (tried to keep it as real as possible).

Let's say that the table CYCLE has client numbers (clientid), cycle number (cycleno), date of visit (visdt).

I am trying to create a query to calculate how many days there are between each two consecutive visits/cycles for a single client(let's say 1200004)

clientid / cycleno / visdt
---------------------------
1200004 / 1 / 10OCT2011
1200004 / 2 / 31OCT2011
1200004 / 3 / 21NOV2011
1200004 / 4 / 05DEC2011
1200004 / 5 / 03JAN2012
...
1000005 / 1 / 04NOV2011
1000005 / 2 / 03DEC2011
1200004 / 1 / 10JAN2012
1200004 / 2 / 15FEB2012
.
.
.

The code below is the only one that kind of seemed to work, but it is definitely not giving me the right results.

SELECT cycleno1, visdt1, cycleno2, visdt2, to_date(visdt1) - to_date(visdt2) days

FROM (SELECT clientid, cycleno cycleno1, visdt visdt1,
LEAD (visdt, 1) OVER (ORDER BY cycleno) visdt2
FROM CYCLE) a

[Code]....

I am getting a mess of a result of the kind:

cycleno1 / visdt1 / cycleno2 / visdt2 / days
--------------------------------------------
1 / 10OCT2011 / 1/ 18OCT2011 / -8
1 / 10OCT2011 / 2/ 18OCT2011 / -8
1 / 10OCT2011 / 3/ 18OCT2011 / -8
1 / 10OCT2011 / 4/ 18OCT2011 / -8
1 / 10OCT2011 / 5/ 18OCT2011 / -8

I need my result to look like:

cycleno1 / visdt1 / cycleno2 / visdt2 / days
--------------------------------------------
1 / 10OCT2011 / 2/ 31OCT2011 / 21
2 / 31OCT2011 / 3/ 21NOV2011 / 22
3 / 21NOV2011 / 4/ 05DEC2011 / 15
4 / 05DEC2011 / 5/ 03JAN2012 / 30
5 / 03JAN2012 / / /
.
.
.

View 3 Replies View Related

Number Of Days Between Dates?

Jan 14, 2008

What I need to do is take 2 dates from a table named 'projects' and insert the number of days between them into a table named 'time_record'.How do I go about this?

View 1 Replies View Related

SQL & PL/SQL :: Month Wise Days For Between Given Dates?

Apr 28, 2010

I have a table with starting date and ending date.

I want to fetch monthwise days for given two dates

IE starting 25/12/2009 ending 25/03/2010

Result should like below.

Dec-09 7
Jan-10 31
Feb-10 28
Mar-10 25

I have tried this but it is not giving me the result which want..

select to_char(thedate,'mon-yy') mnth,count(to_char(thedate,'mon-yy')) days from
(SELECT TRUNC(to_date('25/12/2009','dd/mm/yyyy'),'Y')+ROWNUM-1 THEDATE
FROM ( SELECT 1 just_a_column
FROM dual
CONNECT BY LEVEL <= 366

[code].....

View 3 Replies View Related

SQL & PL/SQL :: How Many Days Thursday And Friday Between Two Dates

Nov 13, 2011

I want function return me how many days Thursday and Friday between two dates.

View 1 Replies View Related

SQL & PL/SQL :: Show Number Of Days Between Two Dates?

Apr 18, 2013

i want to create function to show number of days between to days such as number of Friday days between to dates

View 13 Replies View Related

PL/SQL :: Oracle Dates And Working Days

Sep 5, 2012

Is there an Oracle date function that ignores public bank holidays and calculates working days only?

View 4 Replies View Related

Get Date Difference In Days Between Two Dates In Reports?

Sep 11, 2010

In my server , already 10g r2 is installated , now am installaling 11r2, during this, at final stage while running root.sh , it will propmt to override 3 files, oraenv,dbhome .. etc under /usr/local/bin in solaris sys, as these files are already owned by 10g owner ,what i have to select (y or n)?

what if i select y? it will override three files

what if i select n? default option

View 2 Replies View Related

SQL & PL/SQL :: Finding Individual Dates Having Date Plus 2 Days

Jan 26, 2011

I want to find the dates which have a date plus with in 2 days after this date. I mean group by 3 days each even the date i missing between two days. Actualy I want to find the start date where the employ was missing on job.

Basic concept is employes have allowed to use 10 personal leaves of a year. Each leave can be use for maximum 3 days.

If employ did not come on the job for one day or two days or three days, it shoul be count as ONE personal leave. And If employ is missing at job for four or five days, it should be count as 2 personal leaves.

seq date
------------------------------
101.01.10

205.01.10
306.01.10

410.01.10
512.01.10

613.01.10
714.01.10
815.01.10

916.01.10
1018.01.10

1119.01.10

[Code]...

The result should be (Don't use Pl/Sql)

seq date
------------------------------
101.01.10
205.01.10
310.01.10
413.01.10
516.01.10
619.01.10
723.01.10
826.01.10
929.01.10

After finding these days I want to select the starting date of 5th personal leave. (which is 16.01.10).

I am not a expert of using SQL, but I think it could be possible with using partitioning a table on the givin reslult and further partition the reslut on rownum() as rn and the using case statement where rn = 5.

View 2 Replies View Related

PL/SQL :: How To Calculate Days Between Two Dates Of One Timestamps Field

Sep 25, 2012

how to caluclate days between two dates of single timestamp filed and with this

query
Select * from m_activity_transaction where actn_opp_id in (
Select actn_opp_id from m_activity_transaction where ACTN_ACTV_ID = 218
Group by actn_opp_id

[code]...

and i nedd to caluclate no.of days between two dates like 27-JAN-12 11.06.20.000000 AM and 08-FEB-12 05.32.54.000000 PM where actn_id is unique AND ACTN_OPP_ID IS NOT UNIQUE.

View 6 Replies View Related

SQL & PL/SQL :: Complex Days Computation / Multiple Number Of Same Transaction Dates

May 22, 2010

The data in one of the temporary table has been compiled as below. Number of Days elapsed between two transaction dates is required to be computed and multiplied with the balance. There can be multiple number of same transaction dates. When previous date and the current transaction dates are same the resulting number of day difference should be 0. But when they are different the difference between them is to be computed. On the last day of the Financial Year i.e. '31/03' of any year the difference day should be shown as 1 so as to make 365 or 366 days in a year. Simply deducting d1 from d2 on 31st will not be suffice as the difference is one day less.

----------------------------------------------------------------------------------------- -------
Transaction Narration DebitCreditBalanceNo of DaysProduct
DateDifference
----------------------------------------------------------------------------------------- --------
01/04/2009Opening Balance 45020450277346654
17/06/2009ByAmt5044521253424
29/06/2009By Amt1004352156678912
02/12/2009By Amt424310119476000
[code]....

improve the above code and get the desired output result.

View 5 Replies View Related

Performance Tuning :: How To Find Top Query Running On A Table

Feb 19, 2012

How do i find a particular SQL or a set of SQL's which are excuted against a table (user identified table) that is either a very frequently executed query against that table or high impact SQL against that table? I am currently looking through the AWR reports to go through all the queries but i was wondering if there are any dictionary views where we can find this info from?

View 2 Replies View Related

Performance Tuning :: How To Find Percentage Completion Of Query In Running Status

May 2, 2012

How can we check completion status for running sql query. i.e. how much % completed

SQL> begin
2 delete from gsmcrmdw.wc_loy_txn_f_aa
3 where integration_id in
4 ( select integration_id
5 from support_olap.recover_wc_loy_txn_f_953to955
6 );
7 commit;
8 end;
9 /

View 35 Replies View Related

Performance Tuning :: Removing Nvl Function Then Query Executing In 2 Min Condition

Aug 10, 2011

when am trying to use nvl for one condition it is taking lot of time to execute but when am removing nvl function then the query executing in 2 min. condition is given below

(HOI2.ORG_INFORMATION1)=nvl(TO_CHAR(:p_set_of_books_id) , HOI2.ORG_INFORMATION1)

but when am using the same condition as below the querry executing in 2 min

(HOI2.ORG_INFORMATION1)=TO_CHAR(:p_set_of_books_id)

my query given below

(SELECT cust.customer_number cust_no, cust.customer_name customer,
cnv.item_no, SUM(wd.shipped_quantity) shp_qty_nos,
0 rtn_qty_nos,
ROUND(SUM(cnv.cnf * wd.shipped_quantity), 3) shp_qty_tons,
0 rtn_qty_tons, 0 net_shp_qty_nos, 0 net_shp_qty_tons
[code]...

View 30 Replies View Related

PL/SQL :: To Find Months And Days Between 2?

Oct 9, 2013

 I want to find the months and days between 2 dates. For Eg. Date-1 : 25-Aug-2013Date-2 : 23-Oct-2013 If we consider every month as 30 days it should give 25-Aug-2013 to 30-Aug-2013 = 6 days 01-Sep-2013 to 30-Sep-2013 = 1 Month 23-Oct-2013 to 30-Oct-2013 =   8 days Total = 1 month and 14 days

View 33 Replies View Related

PL/SQL :: How To Find Customer_id Who Placed Orders For Two Days

Apr 8, 2013

I have a customers table like

ORDER_ID CUSTOMER_ID     ORDER_DATE
__________________________________
1     |     100 |25-JAN-13
2     |     100     |25-JAN-13
3     |     100     |24-JAN-13
4     |     101     |23-JAN-13
5     |     101     |22-JAN-13
6     |     102     |21-JAN-13
7     |     102     |21-JAN-13

I would like to find the customer_ids who placed orders for two days.

View 3 Replies View Related

Manually Find Difference In Days And Multiply By 24

Apr 25, 2011

1) First Problem:

Difference in hours is supposed to be 35 but it comes as 34.When i manually find the difference in days and multiply by 24 it comes as 34.999999999 and floor converts it as 34.. But when i execute the difference between dates alone and convert to 24 it shows as 35. So when i apply floor to this, it should be 35 instead of 34 right?

SQL> select (to_date('2011-05-03 09:00:00', 'yyyy-mm-dd hh24:mi:ss') -
2 to_date('2011-05-01 22:00:00', 'yyyy-mm-dd hh24:mi:ss'))
3 from dual
4 ;
[code].....

1) Second Problem:

For the following query, difference of the dates in minutes is 2100.. so mod(2100,60) should give 0 but it's giving 60.. Separately if if put mod(2100,60) it is giving as 0 only.

SQL> SELECT MOD(((to_date('2011-05-03 09:00:00', 'yyyy-mm-dd hh24:mi:ss') -
2 to_date('2011-05-01 22:00:00', 'yyyy-mm-dd hh24:mi:ss')) * 1440),
3 60) AS duration,
4 (to_date('2011-05-03 09:00:00', 'yyyy-mm-dd hh24:mi:ss') -
5 to_date('2011-05-01 22:00:00', 'yyyy-mm-dd hh24:mi:ss')) * 1440 as diffinmin
[code]....

View 2 Replies View Related

SQL & PL/SQL :: Loops - Find All IDs Who Take Tests Within Rolling Window Of 45 Days?

Mar 10, 2012

Main Aim : To find all those id's who have taken all the tests within a rolling window of 45 days.

I have a table "MBS_FIRST_DATE" with the following data :This table has the patients who have the test along with the first date..This table is derived such that it has only one record with the first date of the test irrespective of the test.

create table MBS_FIRST_DATE
(
medical_record_number VARCHAR2(600),
requested_test_name VARCHAR2(39),
result_date DATE

[code]..

Process :will be explaining with a patient id :
1) Consider the patient 1001274 from mbs_first_date table.
2) This patient has an date of July 08th 2008 & test SBP from first table. (keep this test an an anchor).
3) For the patient above loop through the all_recs table with test & result date ordered for the patient. (excluding SBP)
4) The first record we have is CHL with 08/05/2009 (May 8th 2009)..
5) Since this record is not within 45 days from SBP date for the patient..we go to the next record of SBP for the patient.
6) The next record for SBP is 11/05/2009 (May 11th 2009) .
7) Consider the CHL date again which is with 08/05/2009 (May 8th 2009)..
Since both are within 45 days ..store both the values keeping SBP date as an anchor date as it's the test that's having minimum date from table 1. Even though there is one more CHL date which is within 45 days from SBP we don't care about it.
9) Go to the next test for the same patient which is DBP..
10) The DBP first date is July 08th 2008..
11) Since it's not within 45 days from previously stored SBP date (11/05/2009) ignore the record.
12) GO to the next record which is 10/05/2009..as this is within 45 days from SBP & already CHL (stored date) is within 45 days..Grab all the 3 dates as all are within 45 days from anchor date (SBP date).

SO the o/p will be
1001274 SBP 11/05/2009
1001274 CHL 08/05/2009
1001274 DBP 10/05/2009

Code which I wrote :I know some where I am missing the loop

declare
V_ID1 VARCHAR2(200) := '';
V_TEST1 VARCHAR2(200) := '';
V_DATE1 DATE := NULL;

[code]...

View 2 Replies View Related

Emulating MS Office NETWORK DAYS Function

Oct 29, 2010

The MS Office 'NETWORK DAYS' function allows you to subtract one date from another and return the number of 'workdays' between them. So it ignores Sat & Sun. There is an additional parameter that allows you to ignore holidays as well.

I'd like to subtract a 'Request Date' from SYSDATE and get just the number of 'workdays'.

View 3 Replies View Related

Calculate Working Days With Oracle Function

Mar 13, 2009

how do i can make oracle function for the following vb6 function.

This function is used for calculating working days between two date.

****************************************
Public Function Work_Days(BegDate As Variant, EndDate As Variant) As Integer

' Note that this function does not account for holidays.

Dim WholeWeeks As Variant
Dim DateCnt As Variant
Dim EndDays As Integer

On Error GoTo Err_Work_Days
BegDate = DateValue(BegDate)
EndDate = DateValue(EndDate)
WholeWeeks = DateDiff("w", BegDate, EndDate)
DateCnt = DateAdd("ww", WholeWeeks, BegDate)
[code]......

View 3 Replies View Related

SQL & PL/SQL :: Find Two Or More Consecutive Dates?

Feb 23, 2010

I am pulling information from a view to get the current results and placing them into a cursor which then inserts the results into a temp table.

Current Results:
JOB_NAMESCHEDULED_TIME STATUS
JOB_1 02/23/2010 13:25:00Failed
JOB_1 02/22/2010 13:25:00Failed
JOB_1 02/21/2010 13:25:00Failed
JOB_1 02/19/2010 13:25:00Failed
JOB_2 02/21/2010 13:25:00Failed
JOB_2 02/18/2010 13:25:00Failed
JOB_2 02/17/2010 13:25:00Error
JOB_2 02/15/2010 13:25:00Error

Needed Results:
JOB_NAMESCHEDULED_TIME STATUS
JOB_1 02/23/2010 13:25:00Failed
JOB_1 02/22/2010 13:25:00Failed
JOB_1 02/21/2010 13:25:00Failed
JOB_2 02/18/2010 13:25:00Failed
JOB_2 02/17/2010 13:25:00Error

View 5 Replies View Related

SQL & PL/SQL :: Write A Function To Calculate Difference Between Two Dates?

Sep 22, 2011

create or replace function getDate(p_joing_date Date,p_sysdate)
Return Date;
IS
v_compltd_mnths;
BEGIN
SELECT into v_compltd_mnths MONTHS_BETWEEN(TO_DATE('sysdate','MM-DD-YYYY'), TO_DATE('joing_date','MM-DD-YYYY') ) "Months"FROM DUAL;
return v_compltd_mnths;
END;

that i have worte..

View 3 Replies View Related







Copyrights 2005-15 www.BigResource.com, All rights reserved