I have a procedure that needs to be scheduled as a job. This procedure takes an average of 20-25 minutes to complete. The constraint is that these jobs are submitted using dbms_job.submit with an interval of 5 minutes.
So, will Job2 execute only after Job1 completes [even though Job1 takes 25 minutes to complete] or is there any other mechanism for setting incompatibility for a job with itself.
I am trying to install Oracle 9i 32bit client on a windows 2008 server 64 bit OS. In the installation once I select the Oracle home directory and click on Next the whole pc just hangs. Nothing happens. When I checked the Application log I see an error with the following information.
the application (Oracle 9, from vendor Oracle) has the following problem. Oracle 9 is incompatible with this version or windows. For more information, contact Oracle.
Recently we are planning to migrate oracle 10g to 11g. We are migrating PHASE WISE (Schema wise) as this is a 50TB of Production instance. We are using Oracle Golden gate for this purpose.
Is there is any way that we can migrate oracle jobs from 10g to 11g?
I have a requirement where I need to group sessions which takes time as given below when ran individually .There are a total of 32 sesions.I want to divide them into 7 groups.I want to submit each one of the 7 groups in a job.So there will be seven jobs on the whole.Execution flow will be group 1 completes ,then group 2 starts like that.Actually I don't want to bombard the database at a time with 32 jobs ,hence the idea of grouping 32 jobs among 7 groups.grouping the sessions so that on the whole ,resources are equally allocated among sessions in a group and which in turn makes the process complete faster. I want to achieve parallelism but at the same time database should not be loaded too much.I just want to know is there any good practice from oracle side while doing this type of grouping. I am planning to group the most time taking one with least time taking jobs.
My Oracle jobs are not running. I can run them manually but they don't start automatically as per interval. The job_queue_processes=100 and CJQ process is not running. I started CJQ0 process by resetting it to 0 and then to 100. But as soon as I enabled a job this background process stopped.
The job also did not execute in its next execution time. I have created the database manually without using DBCA. Is the problem because of this? I have set crontab immediately to get rid of it.
1) to define a job in oracle9i for solaris 2) to schedule this job
Remember i have prior experience deploying jobs at windows platform but when i try it on (9i for ) solaris, the script does not work as it does not accept a submit job request.
and the error I'm getting is "incompatible versionnumber 3.1 in the dumpfile mydmpfile.dmp"
The dump file was exported using oracle 11.2.0.2.0. I tried to download/unzip the client version of instantclient 11.2.0.2 and add it to the PATH variable in windows and then re-run the script, but it didn't work.
How I should go from here to import this dump file without reinstalling the whole database?
I am working on a report which shows a summarized data from 4 different tables. I have 2 columns which shows certain amount.
The data in both the columns comes from different table.
I want to compare these 2 columns for which i placed a formula column in data model. the code goes this way:
function CF_RECV_PAYFormula return Character is V_RESULT VARCHAR2(50); begin IF :TOTAL_IOU_AMT >= :EXP_AMT THEN
[code].....
The compilation is successful. but when i am running the report i am getting an error Rep-1517 :Column 'CF_RECV_PAY' references column TOTAL_IOU_AMT and EXP_AMT has incompatible frequency.
I have created dataguard between two instances hosted in two different servers. I have done switchover from primary to standby & then again standby to primary with DGMGRL utility.
1- When I done switchover to primary & trying to open standby database in readonly mode it was giving below error-
ORA-01154: database busy. Open, close, mount, and dismount not allowed now
Why this error was coming ?
2- As I was not able to open standby database in read only mode, I have executed below command-
alter database recover managed standby database disconnect from session;
which return an error as-
ORA-01153: an incompatible media recovery is active
After this I have executed-
alter database recover managed standby database cancel;
which executed successfully.
& then after standby database open in read only mode.
Why above error was coming ?
3- After this I had tried to check the checkpoint_change# & controlfile_change# from primary database and result shows both number were different.
I have executed two jobs using dbms_scheduler. The value of the job_queue_process is 10 in my database. It is RAC database with Oracle 10g.
My job gets executed. But the next run is not getting executed at the next run date. In the below example, the systimestamp is 12:27. The first job's next run date is 12:30 so that is fine. But the second job's run date is 12:21 which is 6 mintues less than current time. As a result, the second job does not get executed after this at all..
I am trying to find a way to identify what are the user_jobs currently running. I have found 1 way which requires DBA User ID to execute (e.g. DBA_JOBS and DBA_JOBS_RUNNING) which I don't want.
I believe there is NO equivalent User table for DBA_JOBS_RUNNING table.
I have done my 20 mins search in this forum and unable to find.
am facing an issue with scheduled jobs. The below script will create a scheduled job to insert a record for every 2 mins into the table "job_table".
--Table script CREATE TABLE job_table (now DATE); --Stored procedure run by scheduled job CREATE OR REPLACE PROCEDURE test1 IS BEGIN
[code]...
The scheduled job does not require any special grant privillege as the PUBLIC has access to run it. Anyhow the same set of instruction working for my friend on his machine but not on my environment.
Assign employees to their jobs in consideration the maximum number of employees to each jobs is 5 employee plus each job has own the maximum number of employees
we need the maximum number of employees for each job 5 to be variable when need to change this maximum for certain job , change this number from database (form the from of job ) not form code )
tables emp emp_no name manager hiredate salary
job job_no job
you can add tables or attributes to tables to complete you business.
We are using one application. This application is having 2types of jobs. Under each job again there are each 5 sub jobs. All the jobs are scheduled jobs. Now the requirement is The main 2 jobs we are going to run on some specified days( for this we need to mention on what days we want to run.once we gave those day the next steps will start).
for example 1 main job is scheduled on Monday ( we need to schedule it on monday-- we need to write a program for this) under this every sub job will run.these sub jobs are dependent jobs.if sub job completed successfully it should send an email to the distributed mail group which says like " <Job_name> completed successfully" if it fails also it needs to send an email to the distributed group. for each sub job it should send either success/falure mail to the distriuted mail group.
once after completing all the sub jobs successfully it should send a mail to the distributed mail group saying that The main job got completed successfully.these two main jobs will run paralelly but the the second main job will run after 30 mins of 1st job starts.
in the second job also will work as same as job1 process.it should also send mails to the distributed mail groups.The jobs are already scheduled.No need to scheduled the jobs.need to write a pl/sql program like it will check all the jobs and respected sub jobs if any thing got completed/failed it should send an email to the distributed mail group automatically. For that it should monitor all the jobs..that's the requirement.
I have already scheduled all the jobs. now want to write a script for the above requiement.
i have a production database server with 2 node rac. i now have a separate database server for my report db. Now i want to do an automatic export of the production database or a schema in the production database and then import it automatically to the report db immadiately after the export job finishes at a specific time, say 12 midnight everyday. how do i go about this using crontab or any other better solution. my database is 11gr2 and operating system is rhel 5.7.
We created a job yesterday which will call the below procedure. if we start this job, it initiates 92 sessions parellely. How it is initiating 92 sessions parelley?
procedure prc_HECTOR_CIDB_IN_PURGE IS cursor CUR_PROC is select rowid from CUSTMODEL.HECTOR_CIDB_IN where PROCESS_FLAG in ('Y','F');
TYPE TYP_CUR_DATA IS TABLE OF ROWID INDEX BY BINARY_INTEGER; v_typ_cur_data typ_cur_data; [code]....
Oracle DB Version - 11g XE I scheduled a job using dbms_scheduler which will insert a record into table T for each minute. I didnt mention COMMIT inside my procedure but records are being commited after each successful execution. How come it is possible. Here is my code.
SQL> create table t ( empno number, creation_date date); Table created SQL> create or replace procedure test_proc 2 is 3 4 begin 5 6 insert into t values (1,sysdate); 7 8 end; 9 / Procedure created
Im using APEX 4.0. We startet with APEX 2.2 and upgraded it till 4.0. Database is 10g
The application generates emails which schould be send by APEX background job via APEX_MAIL.PUSH_QUEUE. Currently no mails will be send. Mails are added to APEX_MAIL_QUEUE only. I don´t see anything in columns MAIL_SEND_COUNT and MAIL_SEND_ERROR. Administrators of email server say that they don´t see any attempt to send the mails in our mail queue in mail server logs.
It´s possible to send mails with UTL_SMTP!There is no error produced by APEX push_queue background job.But there are several jobs running:
Ok, it´s possible that´s this is an error of our database administrator.
1. Shouldn´t I see the two background jobs (push_queue, purge_sessions) in schema APEX_0400000? 2. Should I kill push_queue job in schema FLOWS_030100? Where schould the jobs run? 3. How can I debug push_queue? Even if I run it manually I don´t get any return values/errors? 4. Must the jobs have job id 4002 and 4001?